What should a SWPPP inspection form include?

A SWPPP inspection form should capture everything your permit requires in an inspection report. Under EPA's 2022 Construction General Permit that is the inspection date, the names and titles of the inspectors, a summary of findings including maintenance and corrective action needed, the rain reading that triggered a storm inspection, and any area that was unsafe to inspect. The report is due within 24 hours and is signed by the operator's signatory. EPA 2022 CGP Part 4.7.1-4.7.2

National guide. The rules cited are from EPA's 2022 Construction General Permit (as modified in 2025), checked October 20, 2026, which applies where EPA is the permitting authority. Most states issue their own permit with different details; check your state before relying on a number.

Last reviewed October 19, 2026. Prepared by our team led by Mohamed Elansary, PhD. We are not a licensed engineering firm and do not seal plans. General information, not legal advice; the permit text controls.

Which form fits your permit

EPA 2022 CGP areasEPA publishes a Site Inspection Report template, a dewatering inspection report template and a Corrective Action Log template. EPA templates
Texas TXR150000No mandatory TCEQ form; reports must contain the Part III.F.8(f) items, and RG-639 includes inspection worksheets. TXR150000 Part III.F.8(f) RG-639
Other statesUse the report contents your state permit specifies; some states publish a form. See the state hubs: Alaska, Arizona, Arkansas, Colorado, Florida, Hawaii, Idaho, Illinois, Indiana, Iowa, Kentucky, Louisiana, Massachusetts, Michigan, Mississippi, Nebraska, Nevada, New Hampshire, New York, North Dakota, Ohio, Oklahoma, Oregon, South Carolina, South Dakota, Texas, Utah, Washington, West Virginia.

Printable inspection form (EPA 2022 CGP)

Print this page or copy the rows into your own log. Fields follow EPA 2022 CGP Parts 4.6 and 4.7. Adjust the storm trigger to your state permit if the state is the permitting authority.

ItemEntry
Site name, permit or NPDES ID 
Inspection date and start time 
Inspector names and titles (training proof kept in the SWPPP) 
Inspection type: 7-day / 14-day / storm (0.25 in. rain or 3.25 in. snowmelt) / stabilized area / dewatering 
Rain gauge or weather station reading that triggered the inspection 
Controls installed and working? Note each one not working 
Spill, leak or pollutant accumulation risks found 
Locations needing new or modified controls 
Visible erosion or sediment at discharge points, banks, streets, curbs 
Discharge occurring? Points, color, odor, solids, foam, sheen 
Areas unsafe to inspect, reason and location 
Maintenance needed (fix by end of next business day) 
Corrective action needed (new control within 7 days); log entry made? 
Noncompliance observed 
SWPPP or site map change needed (within 7 days) 
Signature of the operator's signatory and date 

Rules the form supports

Dewatering inspections and the corrective action log

On each day of a dewatering discharge, inspect and record the details Part 4.6.3 lists for dewatering. EPA 2022 CGP Part 4.3.2, 4.6.3 Corrective action needs its own log: the condition and when it was found, within 24 hours, then the actions taken within 24 hours of completing them, each entry signed, kept on site and retained 3 years. EPA 2022 CGP Part 5.4.1-5.4.4

Common gaps in inspection forms

What this page does not cover

State-specific forms beyond the examples above, inspector training or certification, and inspection software.

Have it written for you

SWPPP Desk prepares site-specific SWPPPs from your drawings for construction sites in the states we cover (coverage by state), for a fixed price, delivered the next business day after your inputs are complete. Small site (1 to under 5 acres): $449. Large site (5 acres or more): $749. Background: all guides.