Checked October 20, 2026 against the permit text published by Washington State Department of Ecology. Sources and sections are listed at the end of this page.
In Washington, construction stormwater coverage comes from Construction Stormwater General Permit (permit no. WAR3xxxxx coverages under the CSWGP), issued by Washington State Department of Ecology. It took effect January 1, 2026 and expires December 31, 2030.
Where we can help. You provide a Certified Erosion and Sediment Control Lead (CESCL) for inspections (S4.B). Weekly sampling and a 60-day NOI with public notice also apply.
At a glance
| Item | What the permit says |
|---|---|
| How coverage is obtained | NOI at least 60 days before discharge (S2.A) plus newspaper public notice once a week for 2 consecutive weeks (S2.B) |
| Agency fee | Annual fees under Chapter 173-224 WAC (S6) |
| Who may prepare the plan | No license or seal for the SWPPP (S9); engineering calcs must be included when designed structures are used |
| Who inspects | Certified Erosion and Sediment Control Lead (CESCL) for sites 1 acre or more (S4.B) |
| Inspection frequency | CESCL at least once every calendar week and within 24 h of any discharge (S4.B); weekly turbidity/transparency sampling (S4.C) |
| State forms and templates | Ecology SWPPP template available (not mandatory) |
Points that are easy to miss
- Plan for the 60-day NOI window and two newspaper notices.
- CESCL required for inspections.
- Weekly turbidity and pH sampling with monthly DMRs.
What a SWPPP Desk plan covers here
We prepare a site-specific plan written to WAR3xxxxx coverages under the CSWGP, with each section mapped to the permit part it answers. You, the operator, review and sign it and keep it on site.
Checkout open in Washington. State ruling: Sell (client supplies CESCL). The site check on the plan page applies these conditions before payment. See coverage.
Before checkout you confirm:
- You will supply a Certified Erosion and Sediment Control Lead (CESCL) for the inspections.
What we do not do
- Our plans are not sealed or stamped. BMPs that need design calculations, such as sediment basins and post-construction practices, come from your design professional.
- The operator signs the plan and is responsible for it.
- We do not visit or inspect sites.
- We do not file the NOI or any permit application for you. We tell you which form and portal the permit names.
Sources
- Permit text: fortress.wa.gov (S2.A, S2.B, S4.B, S4.C, S6, S9). Checked 2026-10-20.