What is TXR150000, the TCEQ construction general permit?

TXR150000 is the Texas Pollutant Discharge Elimination System (TPDES) Construction General Permit (CGP) issued by TCEQ. It authorizes stormwater discharges from construction that disturbs one acre or more. The current permit took effect March 5, 2023 and expires March 5, 2028; TCEQ has started the renewal. TCEQ

Last reviewed October 19, 2026. Prepared by our team led by Mohamed Elansary, PhD. We are not a licensed engineering firm and do not seal plans. General information, not legal advice; the permit text controls.

Key facts

IssuerTexas Commission on Environmental Quality (TPDES program). TCEQ
Effective / expiresMarch 5, 2023 / March 5, 2028. TCEQ
RenewalTCEQ held a renewal stakeholder meeting on June 9, 2026; informal comments closed June 23, 2026. TCEQ
CoversStormwater from construction disturbing 1+ acres (or part of a larger common plan) that discharges to surface water in the state, plus construction support activities such as batch plants, equipment staging and borrow areas. TCEQ TXR150000 Part I.B
ScaleTCEQ reported 14,572 active NOIs under the CGP as of October 2023. TCEQ seminar slides
Filing systemNOI, LREW, NOT and NOC are filed in STEERS unless you hold an electronic reporting waiver. TCEQ

How the permit is organized

TXR150000 table of contents

Who it applies to

Disturbed areaTCEQ classKey obligations
Under 1 acre, not part of a larger common plan of 1+ acresNot regulated by the CGPNo CGP coverage needed. TCEQ
1 to under 5 acres (or part of a common plan in that range)Small construction activitySWP3 before work; post Form 20963 at least 2 days before work; copy to MS4 operator 2 days before; no NOI. TXR150000 Part II.E.2
5 acres or more (or part of a 5+ acre common plan)Large construction activitySWP3 before coverage; primary operator files NOI in STEERS before work; post Form 20961 or 20962. TXR150000 Part II.E.3

What a large-site NOI asks for

At minimum: operator name, address and phone; site name, address, county and latitude/longitude; acres disturbed; estimated start and end dates; and confirmations including that a SWP3 has been developed and will be implemented before construction. TXR150000 Part II.E.6 See TCEQ NOI.

Not eligible

A facility with an "unsatisfactory" compliance history ranking cannot use the general permit and must apply for an individual permit. TCEQ Data-center projects are currently halted. TCEQ notice

What this page does not cover

EPA's Construction General Permit (for areas where EPA is the permitting authority), industrial stormwater permit TXR050000, and the outcome of the 2028 renewal.

Have it written for you

SWPPP Desk prepares site-specific SWPPPs from your drawings for construction sites in the states we cover (coverage by state), for a fixed price, delivered the next business day after your inputs are complete. Small site (1 to under 5 acres): $449. Large site (5 acres or more): $749. Background: all guides.