SWPPP requirements in Dallas, Texas
In Dallas, all construction, regardless of size, must comply with Dallas City Code Sec. 19-118. Sites of 1 acre or more also follow TCEQ's Construction General Permit, TXR150000, as small (1 to under 5 acres) or large (5+ acres) construction sites.
Last reviewed October 19, 2026. Prepared by our team led by Mohamed Elansary, PhD. We are not a licensed engineering firm and do not seal plans. Local rules change; confirm with the city before you start.
Local requirements in Dallas
- All construction activities in Dallas, regardless of size, must comply with Dallas City Code Sec. 19-118. Source
- Sites of at least 1 and under 5 acres follow the TXR150000 small-site rules, and sites of 5 acres or more follow the large-site rules, in addition to City Code requirements. Source
- Dallas Stormwater Management accepts TCEQ CGP notices (NOI, Construction Site Notice, NOC and NOT) only by email to SWMsubmittals@dallas.gov; it no longer accepts hand-delivered notices or notices emailed to individual staff. Questions: 214-948-4022. Source
- Under TXR150000, small sites give the MS4 operator a copy of the signed site notice at least 2 days before construction. Source
Scope flags
We found no city requirement for a sealed SWP3 on the Dallas pages we reviewed. If your project has BMPs that need engineering design, a sediment basin, impaired receiving waters or a locally required sealed plan, it is out of scope, and the checkout gate stops the order before payment.
State rules that apply everywhere in Texas
| Disturbed area | TCEQ class | Key obligations |
|---|---|---|
| Under 1 acre, not part of a larger common plan of 1+ acres | Not regulated by the CGP | No CGP coverage needed. TCEQ |
| 1 to under 5 acres (or part of a common plan in that range) | Small construction activity | SWP3 before work; post Form 20963 at least 2 days before work; copy to MS4 operator 2 days before; no NOI. TXR150000 Part II.E.2 |
| 5 acres or more (or part of a 5+ acre common plan) | Large construction activity | SWP3 before coverage; primary operator files NOI in STEERS before work; post Form 20961 or 20962. TXR150000 Part II.E.3 |
Checklist for a Dallas site
- Confirm acreage class (count support activities).
- Prepare and implement the SWP3 before soil disturbance. TXR150000 Part III.C
- Large sites: file the NOI in STEERS ($225 online). Small sites: sign Form 20963. TCEQ
- Send the NOI or site notice copy to the local MS4 contact above, on the local deadline.
- Post the site notice; keep the SWP3 on site; inspect on your chosen schedule. TXR150000 Part III.D, III.F.8
- At final stabilization, terminate and send the local copy. Keep records 3 years. TXR150000 Part VII
What this page does not cover
Building, grading or site development permits, drainage criteria, post-construction water quality permits (except where flagged above), and neighboring cities or county jurisdictions.